Timeline

 

In addition, the following schedule is what the project team will be relying on to follow: 

  • Last Regular Migration to Prod: Wednesday, 9/4
  • Final Break-Fix: Wednesday: 9/11
  • Performance/Regression Testing Sign-Off: Thursday 9/12
  • Quiet Period: 9/13-9/26
  • Go-Live Walk-Through: TBD, week of 9/16, details forthcoming
  • Data Warehouse Testing Sign-Off: Wednesday 9/25 (moved from 9/6)

Data Migration / AWS Move:

  • Thursday 9/26
    • Last data warehouse (DW) loads ~8am
    • View-Only PS access begins ~9pm
  • Friday 9/27 - Saturday 9/28
    • Data migration occurs
    • View-Only PS access continues
  • Sunday, 9/29
    • Sierra-Cedar (SCI) & ASU Validations
    • View-Only PS access ends (no user access)
  • Monday, 9/30
    • Verification Window (Time TBD)
    • Normal PS access anticipated by 8am

Migration paths (PS Systems team will verify object impacts before migration to Production):

● Projects with impacts DEV → SUP→ PRD

● Projects with no impacts DEV → TST → PRD