In addition, the following schedule is what the project team will be relying on to follow:
- Last Regular Migration to Prod: Wednesday, 9/4
- Final Break-Fix: Wednesday: 9/11
- Performance/Regression Testing Sign-Off: Thursday 9/12
- Quiet Period: 9/13-9/26
- Go-Live Walk-Through: TBD, week of 9/16, details forthcoming
- Data Warehouse Testing Sign-Off: Wednesday 9/25 (moved from 9/6)
Data Migration / AWS Move:
- Thursday 9/26
- Last data warehouse (DW) loads ~8am
- View-Only PS access begins ~9pm
- Friday 9/27 - Saturday 9/28
- Data migration occurs
- View-Only PS access continues
- Sunday, 9/29
- Sierra-Cedar (SCI) & ASU Validations
- View-Only PS access ends (no user access)
- Monday, 9/30
- Verification Window (Time TBD)
- Normal PS access anticipated by 8am
Migration paths (PS Systems team will verify object impacts before migration to Production):
● Projects with impacts DEV → SUP→ PRD